BUREAU OF ADMINISTRATION PROCEDURES
FOR DESIGN-BUILD PROCUREMENT OF
DEPARTMENT OF TRANSPORTATION
HIGHWAY CONSTRUCTION PROJECTS
(Best Value Process)
Purpose
In order to comply with the requirements of the Design-Build Procurement Act, the Department of Transportation shall select design-build firms to provide combined design and construction services for authorized highway construction projects in accordance with the following procedures.
Definitions
For purposes of this procedure the definitions contained in the Design-Build Procurement Act and the following definitions apply:
Minimum Qualification Requirements for Firms Providing Design-Build Services
Design-builders shall be registered with the Secretary of State and the Department of Revenue prior to contract award. Where required by state or federal law, the design-builder shall be able to provide design or construction services by licensed or registered individuals.
Public Announcement Procedures
Except in emergency situations, the Department shall publish an announcement in accordance with SDCL §5-18-3. The announcement shall set forth a general description of the project requiring design-build services and defining time frame and procedures for interested qualified firms to apply for consideration. The public announcement shall further state whether design-builders will be pre-qualified for the project.
Technical Review Committee
There shall be a Technical Review Committee (Committee) comprised of the following:
The Committee shall have responsibility for determination of the most qualified offerors as provided in "Qualification of Design-Builders" and rating and scoring Qualitative Proposals as provided in "Competitive Selection of Design-Build Services".
Criteria Package and Request for Proposals
(1.) The Department shall prepare a criteria package. The criteria developer may be either a private practitioner (selected in accordance with normal procedures for selecting design firms) or on the staff of the Department or other state agency. The criteria developer is prohibited from being part of the bidding entity. The criteria package may include the following:Scope of work;
(2.) The purpose of the criteria package is to furnish sufficient information for firms to prepare qualitative proposals and price proposals. The firm submitting the successful proposal shall develop a detailed project design based on the criteria in the criteria package. Moreover, the firm shall construct the facility in accordance with the criteria package.
(3.) The Request for Proposals ("RFP") shall consist of the criteria package, instructions to bidders, bid proposal forms, provisions for contracts, general and special conditions, and basis for evaluation of proposals.
Qualification of Design-Builders
(1.) The Department shall qualify design-builders on a project by project basis.
(2.) The Department shall advertise in accordance with SDCL § 5-18-3
for a Request for Qualifications ("RFQ") . The RFQ shall contain the following:
a general description of the project;
Firms desiring to submit proposals on the design-build project shall submit a statement of qualifications setting forth the qualifications of the entities involved in the firm and providing any other information required by the RFQ.
(3.) The Committee shall determine the relative ability of each D-B team to perform the services required for each project. The Committee shall base its determination upon the following:
(4.) The Committee shall select at least two and no more than five firms deemed to be most highly qualified to perform the required services, after considering the factors in (2) above. The Committee will report its selection of most highly qualified offerors to the State Highway Engineer.
(5.) The State Highway Engineer shall issue RFP's to the most highly qualified firms selected by the Committee.
Competitive Selection of Design-Build Services
- Qualitative Proposal. A qualitative proposal shall include preliminary design drawings, outline specifications, technical reports, calculations, permit requirements, management plan, schedule, and other data requested in response to the RFP. Qualitative proposals shall be submitted in a sealed package, which identifies the project and the design-builder on the outside of the package. Each firm shall place the words "QUALITATIVE PROPOSAL" on the outside of the package. Nothing contained in the qualitative package, except the project management plan set forth below shall identify the design-builder. The project management plan shall be submitted in a separate envelope within the qualitative proposal package.
- Price Proposal. Price proposals shall include one lump sum cost for all design and construction of the proposed project. Each firm shall submit its price proposal in a separate sealed package. Each firm shall place the words "PRICE PROPOSAL" on the outside of the package. Each firm shall also place its name, the project description, and any other information required by the RFP on the outside of the package. The Department shall secure price proposals until the time provided in "Best Value Selection", paragraph (1).
| 1. Technical Criteria | Maximum Score: 65 |
| 2. Project-specific Management Plan | Maximum Score: 20 |
- Management Plan and Organization
- Resumes of Key Professional and Managerial Personnel
- Quality Assurance Plan
- Safety Plan
- Minority and Disadvantaged Business Participation Plan
3. Project Schedule Maximum Score: 15
- Construction Schedule and Ability to Meet Schedule
- Architecture and Engineering Design Schedule and Ability to Meet Schedule
- Length of Construction and Design Schedule
Total Maximum Score: 100
The Committee may adjust and refine all of the above criteria and the points assigned to each based on the project type and Department experience. The Committee may reduce the weight of management criteria or omit it entirely if it is sufficiently determinative in selection of the most qualified offerors under "Qualification of Design-Builders". The Committee may omit schedule as criteria when it is a fixed requirement in the RFP.
Best Value Selection and Award for Design-Build Services
Firm |
Qualitative Score |
Proposed Price |
Adjusted Price |
A |
90 |
$6.9 million |
$7.67 million |
B |
79 |
$6.3 million |
$7.97 million |
C |
84 |
$6.8 million |
$8.09 million |
(Award to Firm A at $6.9 million)